The project manager for a TV tower construction project receives notification that a strong storm is expected the following week.
Which of the foll
owing should the project manager do NEXT?
A. Evaluate the risk, inform major stakeholders about the problem, and issue a change request immediately.
B. Evaluate the risk, fill in the issue log, and communicate it according to the communication plan.
C.
Evaluate the risk, develop a mitigation plan, and communicate it according to the communication plan.
D. Evaluate the risk, reschedule all outdoor tasks for a later time, and inform major stakeholders.
References: Kim Heldman, CompTIA Project+ S