A customer has requested additional features for an active project.

A customer has requested additional features for an active project.

Which of the following steps should take place NEXT?

A. Implement the requested changes.

B. Evaluate the impact of the ch

anges.

C. Update all project documents.

D. Submit the requested changes to the CCB.

References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p.