The project manager has noticed a vendor is not performing in accordance with the SLA.
Which of the following items should the project manager use to highl
ight the vendor-s areas of poor performance?
A. Balanced score card
B. WBS
C. Post-project evaluation
D. PERT
References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 332