A project manager provides status reports to a customer on a biweekly basis, but the customer is very busy and

A project manager provides status reports to a customer on a biweekly basis, but the customer is very busy and only has a few

minutes to review the project.

Which of the following are critical for the project manager to provide?

A. Cost, schedule, organizational chart, and risks/issues

B. Risks/issues, cost, RACI chart, and action items

C. Schedule, cost, risks/issues, and mile

stones

D. Action items, organizational chart, schedule, and NDA

References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 326