PrepAway - Latest Free Exam Questions & Answers

3An authorized change to a construction project was implemented. During the modification, the team identified

3

An authorized change to a construction project was implemented. During the modification, the team identified a defect in which the change caused the building power output to be outside the KPPs.

Which of the following actions should the project manager

take?

A. Submit a new change request.

B. Initiate the regression plan.

C. Add remediation to the schedule.

D. Accept the new power output.

References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p.

294


Leave a Reply