If a project sponsor wants to know the current status and progress of a project, which of the following is the

If a project sponsor wants to know the current status and progress of a project, which of the following is the BEST approach to find this information?

A. The project sponsor should obtain the current status

from team members, put it into a presentation, and present it to the project manager for review.

B. The scheduler should obtain the current status from team members, apply it to the baseline of the schedule, and run a report.

C. The scheduler should obtain

the current status from team members, update the project charter, project management plan, dashboard, and SOW, and then create a status report to provide to the project manager.

D. The scheduler should obtain the current status from team members, update t

he risk register, and provide the information to the project champion for review.