A project manager has contracted a third-party vendor to achieve milestones. Which of the following risk strat

A project manager has contracted a third-party vendor to achieve milestones. Which of the following risk strategies is the project

manager applying?

A. Transfer

B. Accept

C. Avoid

D. Mitigate

References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 238