A project manager has contracted a third-party vendor to achieve milestones. Which of the following risk strategies is the project
manager applying?
A. Transfer
B. Accept
C. Avoid
D. Mitigate
References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 238