Two team members completely disagree on how to complete a specific task. The project manager observes the conf

Two team members completely disagree on how to complete a specific task. The project manager observes the conflict but takes no immediate action.

Which of the following techniques is the project manager using?

A. Compromising

B. Smoothing

C. Withdrawing

D. Accepting

References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 200