Which of the following metrics demonstrates to a project manager if a pro…

Which of the following metrics demonstrates to a project manager if a pro

ject is overspending or underspending?

A. EAC

B. BAC

C. CPI

D. ETC

References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 231