Which of the following is the MOST likely target audience to be notified of the achievement of a key milestone

Which of the following is the MOST likely target audience to be notified of the achievement of a key milestone in a project schedule?

A. Project manager and project scheduler

B. Project coordinator and project sponsor

C. Project champion and project scheduler

D. Project stakeholders and project team

References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 326