PrepAway - Latest Free Exam Questions & Answers

An outsourced project team member approaches the project manager and complains that the contract does not perm

An outsourced project team member approaches the project manager and complains that the contract does not permit overtime. The project manager had fast-tracked tasks that require addi

tional hours. Which of the following documents did the project manager fail to reference?

A. MOU

B. MOA

C. SOW

D. SLA


Leave a Reply