An organization has multiple projects that are taking place simultaneously.
Which of the following should be tasked with ensuring reso
urces are appropriately allocated to projects?
A. PMO
B. Project sponsor
C. Project coordinator
D. HR
References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 82