A new stakeholder has joined the project team and requested modifications that will result in minor changes to

A new stakeholder has joined the project team and requested modifications that will result in minor changes to the project budget and schedule.

The project manager is concerned that the requests will lea

d to:

A. quality control issues.

B. additional risks.

C. scope creep.

D. time constraints.