A critical stakeholder has requested additional status updated beyond the schedule.

A critical stakehol

der has requested additional status updated beyond the schedule.

Which of the following factors MOST likely needs to be accounted for when communicating with this stakeholder?

A. Confidentiality

B. Criticality

C. Frequency

D. Cultural differences

References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 265