PrepAway - Latest Free Exam Questions & Answers

A project manager is managing a project with a hard deadline in two week…

A project manager is managing a project with a hard deadline in two week

s. At the current rate of progress, the project will not finish on time.

Which of the following techniques is MOST likely to be used to complete the project on time?

A. Throttling

B. Crashing

C. Resource leveling

D. Resource smoothing

References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 170