A company has dictated project scope changes but has stated that the original budget still applies. Which of the followin
g will MOST likely be impacted by the changes?
A. Quality
B. Regulations
C. Schedule
D. project team
References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 133