PrepAway - Latest Free Exam Questions & Answers

A program manager informs a project manager that a new, high-priority project has been approved and will need

A program manager informs a project manager that a new, high-priority project has been approved and will need the current project-s resources before the scheduled project close date. The project team meets and determines that th

e project should be fast-tracked.

Which of the following documents should the project team reference to fast-track the project? (Choose two.)

A. Scope management plan

B. Configuration management plan

C. Network diagram

D. Project schedule

E. Project plan

References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 171


Leave a Reply