A program manager informs a project manager that a new, high-priority project has been approved and will need the current project-s resources before the scheduled project close date. The project team meets and determines that th
e project should be fast-tracked.
Which of the following documents should the project team reference to fast-track the project? (Choose two.)
A. Scope management plan
B. Configuration management plan
C. Network diagram
D. Project schedule
E. Project plan
References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 171