A project team has purchased computers with warranties extending throughout the entire project. Which of the f

A project team has purchased computers with warranties extending throughout the entire project. Which of the following represents the risk strategy utilized?

A. Transfer

B. Share

C. Mitigate

D. Avoid

References: https://teamweek.com/blog/2017/