PrepAway - Latest Free Exam Questions & Answers

A milestone task on the critical path has been completed.

A milestone

task on the critical path has been completed.

Which of the following should the project manager notify?

A. Owner of predecessor task

B. Project team

C. Project sponsor

D. Project steering committee


Leave a Reply