A project-s key stakeholders have requested significant changes that will affect the scope. To adjust the proj

A project-s key stakeholders have requested significant changes that will affect the scope. To adjust the project scope, which of the follow

ing need to be changed? (Choose two.)

A. Cost performance parameter

B. Project schedule

C. KPI

D. Corrective action plan

E. WBS

References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 133