A project-s key stakeholders have requested significant changes that will affect the scope. To adjust the project scope, which of the follow
ing need to be changed? (Choose two.)
A. Cost performance parameter
B. Project schedule
C. KPI
D. Corrective action plan
E. WBS
References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 133