A carpenter on a
project team reports there is insufficient time to accomplish tasks on schedule.
Which of the following is the FIRST step the project manager should take?
A. Assess the risk register-s new items.
B. Review the task start and finish dates.
C. Obtain addit
ional resources.
D. Analyze the assigned hours.