A project manager needs to identify the resources assigned to a particular task.
In which of the following documents can this information be found?
A. Project schedule
B. Cost plan
C. Scope statement
D. Impact assessment
References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 156