A project manager needs to identify the resources assigned to a particular task.

A project manager needs to identify the resources assigned to a particular task.

In which of the following documents can this information be found?

A. Project schedule

B. Cost plan

C. Scope statement

D. Impact assessment

References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 156