Team members have reported that meetings are poorly attended and unproductive.
Which of the following steps can the project manager take to make the meetings more productive?
A. Discontinue th
e meetings with the poorest attendance.
B. Decrease the length of the meetings.
C. Distribute an agenda before each meeting.
D. Document team member attendance and report it to management.
References: Kim Heldman, CompTIA Project+ Study Guide,
2nd Edition, Sybex, Indianapolis, 2017, p. 326