A project team is composed of…

A project team is composed of

numerous team members who are located throughout a country. All personnel have identified core business hours. A team engineer based in a machine shop has a question during business hours for the project manager, who is located at a different facility.

Wh

ich of the following is the MOST expedient communication method, assuming the question can be resolved quickly?

A. Email

B. Social media

C. Text messaging

D. Face-to-face

References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition,

Sybex, Indianapolis, 2017, p. 261