Which of the following measurements would give the project manager the BEST estimate of the total cost of an active project?
A. EAC
B. BAC
C. TCPI
D.
ETC
References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 232