A customer will have ongoing changes to project requirements.
Which of the following is the BEST project management meth
odology for this requirement?
A. Waterfall
B. Agile
C. PRINCE2
D. Bottom-up
References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 310