A customer will have ongoing changes to project requirements.

A customer will have ongoing changes to project requirements.

Which of the following is the BEST project management meth

odology for this requirement?

A. Waterfall

B. Agile

C. PRINCE2

D. Bottom-up

References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 310