During the initiation phase, a

project manager has asked for a document containing the high-level objectives and goals for a project.

Which of the following documents would contain these items?

A. Business case

B. Requirements document

C. Project timeline

D. Task plan

Refer

ences: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 138