A project manager was directed to complete a project sooner than previously planned. Which of the following is

A project manager was

directed to complete a project sooner than previously planned. Which of the following is the MOST cost effective step to take to ensure the project-s success?

A. Reduce the scope

B. Increase the budget

C. Decrease staff

D. Update the WBS