A project manager noticed the develo

pment team supporting a project does not have sufficient skills to complete the development phase. The project manager has discussed this issue with the functional manager and agreed to continue with the development phase due to time restrictions.

Which o

f the following strategies is the project manager applying?

A. Accepting

B. Mitigating

C. Avoiding

D. Transferring

References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 238