Due to a new government regulation, a project change is required. The project manager evaluates the change and

Due to a new government regulation, a project change is required. The project manager evaluates the change and realizes a representative from the legal department will need to approve the

change as well.

The project manager should:

A. follow the change process flow and notify the legal department after the change is implemented.

B. extend a formal invitation to the legal department representative to join the CCB.

C. hold a separate meetin

g with the legal department representative and ask for approval.

D. notify the legal department representative in the event of an upcoming audit.

References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 2