A project coordinator logs potential events that can affect project constraints, and t

hen records the results of brainstorming of potential strategies.

Which of the following documents should the project coordinator use?

A. Risk register

B. Issue log

C. Communication plan

D. Status report

References: Kim Heldman, CompTIA Projec

t+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 240