A critical stakehol
der has requested additional status updated beyond the schedule.
Which of the following factors MOST likely needs to be accounted for when communicating with this stakeholder?
A. Confidentiality
B. Criticality
C. Frequency
D. Cultural differences
References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 265