You are the project manager and now in the middle of creating RFP (Request for Proposal) RFTP (Request for pro

You are the project manager and now in the middle of creating RFP (Request for Proposal) RFTP (Request for proposal) is done in ______________________

PrepAway - Latest Free Exam Questions & Answers

A.
Plan procurement

B.
Conduct procurement

C.
Administer Procurements

D.
Close procurements