You are the project manager for the software Project. This project must be completed within one year. This is an example of which of the following?

PrepAway - Latest Free Exam Questions & Answers

A.
Schedule

B.
Assumption

C.
Constraint

D.
Planning Process

Explanation:
A project must be completed by a deadline is dealing with time constraints.