what you tell ?

Is a project with a SPI of 1.8, what you tell ?

PrepAway - Latest Free Exam Questions & Answers

A.
The project is runnig ahead of the schedule

B.
The project is running behind of the schedule

C.
Resources assigned to the project cost 1.8 units

D.
None

Explanation:
The SPI= EV/PV. A schedule performance Index of 1 or greater suggests that the project is aahead of schedule.