Your project has an EV of 100 work-days, an AC of 120 work days, and a PV of 80 work days. What should be your concern?

PrepAway - Latest Free Exam Questions & Answers

A.
There is a cost under run

B.
There is a cost overrun

C.
May not meet deadline

D.
The project is 20 days behind schedule