Which of the following is a common characteristic of most project life cycle descriptions?

Which of the following is a common characteristic of most project life cycle descriptions?

PrepAway - Latest Free Exam Questions & Answers

A.
Cost and staffing are low at the start higher towards the end and drop rapidly as the project nears completion

B.
The probability of succesfully completing the project is highest at the start of the project

C.
Stakeholders have the most influence on the final characteristics of the product at the end of the project

D.
A and B

Explanation:
Project Life cycle : Cost and staffing Levels