Forecasts, requested changes, recommended corrective actions, and organizational process asset updates are all outputs of which process?

PrepAway - Latest Free Exam Questions & Answers

A.
Risk response planning

B.
Risk monitoring and controlling

C.
Performance reporting

D.
Manage stakeholders

Explanation:
Performance Reporting is:
The process of gathering and communicating information regarding the current status of a project as well as projections for progress over time.
Durng performance reporting:

Information regarding the work being accomplished
resources being used is collected, analysed and displayed in various report formats.