In PMBOK the buyer is ______________ to the project team

In PMBOK the buyer is ______________ to the project team

PrepAway - Latest Free Exam Questions & Answers

A.
Internal

B.
External

C.
Outside

D.
Assigned

Explanation:
Internal to the project team