What is the actual status of this project?

The project manager calculated a schedule performance index 0.80 and a cost performance index 1.1 for the project. What is the actual status of this project?

PrepAway - Latest Free Exam Questions & Answers

A.
Behind the schedule and over budget

B.
Behind the schedule and under budget

C.
Ahead of schedule and under budget

D.
Ahead of schedule and over budget

Explanation:
Schedule performance Index (SPI) = EV/PV is an indicator whether the project is on time (SPI = 1) or behind the schedule(<1).

Cost performance Index (CPI) = EV/AC is an indicator whether the project is incurring expenses more than (CPA<1)/less than(CPI >1)/ equal to (CPI = 1)