A major assumption of all network schedulling methods is that the activity duration must be ________________

A major assumption of all network schedulling methods is that the activity duration must be ________________

PrepAway - Latest Free Exam Questions & Answers

A.
Statistically dependent

B.
Variance distributed

C.
Statistically independent

D.
Deterministic