what Project Time Management Process?

Activity resource requirement and resource breakdown structure are outputs from what Project Time Management Process?

PrepAway - Latest Free Exam Questions & Answers

A.
Schedule Control

B.
Activity Definition

C.
Schedule Development

D.
Activity Resources Estimating