A project Cost Mangement plan is created as a part of:

A project Cost Mangement plan is created as a part of:

PrepAway - Latest Free Exam Questions & Answers

A.
Develop Project Management Plan process

B.
Control Cost Process

C.
Determine Budgets Process

D.
Estimate Cost Process

Explanation:
Ther is no separate process in the Project cost estimation Knowledge area to develop a cost management plan. It is developed in Develop Project Management Plan process