what you tell??

If a project with a SPI of 0.80 what you tell??

PrepAway - Latest Free Exam Questions & Answers

A.
Project is running ahead of the schedule

B.
Project is running behind of the schedule

C.
Resources assigned to the project cost 1.8 units

D.
None

Explanation:
SPI stands for Schedule Performance Index.
It is a very powerful measure of the amount of work actually completed on a project. It is part of the Earned Value Management Techniques.
To calculate SPI for any project, get the Planned Value and the Earned Value. The formula for SPI is
SPI = EV / PV

As a rule of thumb, for Schedule performance index (SPI), EV/PV greater than 1 is good (ahead of schedule), and less than 1 is bad ( behind schedule).