The scope management plan is a subsidiary of which project document?
A.
Schedule management plan
B.
Project management plan
C.
Quality management plan
D.
Resource management plan
Explanation:
The Scope Management Plan only tells you how to manage the scope how the requirements are collected, how are they documented, how are they verified, prioritised, updated, changed etc. But the scope management plan itself is never part of the Scope Baseline. It is the other way round – The Scope Baseline is part of the Scope Management Plan.The Scope Management Plan only tells you how to manage the scope how the requirements are collected, how are they documented, how are they verified, prioritised, updated, changed etc. But the scope management plan itself is never part of the Scope Baseline. It is the other way round – The Scope Baseline is part of the Scope Management Plan.