The main purpose of project initiation is to ________________
A.
Assign the project manager to the project
B.
Formally describes the project
C.
Produce the project charter
D.
Formally authorize the project
Explanation:
Output of project initiation is Formally authorize the project. Output of project scope initiation is: Project Charter PM assigned Constraints and Assumptions.