Which is the most important element of a Project Management Plan that is usefull in the Develop Human resources Plan Process
A.
Risk Manahgement activities
B.
Activity Resources Requirements
C.
Budget Control Activities
D.
Quality Assurance Activities
Explanation:
Activity resource requirements. This is normally a document that describes the number of resources for each schedule activity, and the knowledge, skills and experience of each. The work effort may be described as total hours, or as skills set per time period. An example for the latter might be three bricklayers for a period of two weeks. It is helpful to include assumptions and other detail in support of such estimates for each activity.