Rolling wave planning is used as tool and technique in which of the following processes?
A.
Estimate Activity Durations
B.
Define Activities
C.
Develop Schedule
D.
Sequence Activities
Explanation:
Rolling wave planning is the process of planning for a project in waves as the project becomes clearer and unfolds. It is important in such projects to at least highlight in the initial plan the key milestones for the project.