What type of planning is used where the work to be accomplished in the near term is planned in detail, while w

What type of planning is used where the work to be accomplished in the near term is planned in detail, while work in the future is planned at a higher level?

PrepAway - Latest Free Exam Questions & Answers

A.
Finish-to �start planning

B.
Rolling wave planning

C.
Short term planning

D.
Dependency determination

Explanation:
Rolling wave planning is a project management technique that involves progressive elaboration to add detail to the Work Breakdown Structure (WBS) on an ongoing basis. At the beginning of the project, near term deliverables are decomposed into individual components (work packages) and defined at the greatest level of detail. Deliverables and schedule activities that will take place several reporting periods in the future are more broadly defined