PrepAway - Latest Free Exam Questions & Answers

which of the following is a logical relationship for the activities?

In the precedence diagramming method, which of the following is a logical relationship for the activities?

PrepAway - Latest Free Exam Questions & Answers

A.
Finish-to-start

B.
Applying leads and lags

C.
Activity-on-node

D.
Dependency determination

Explanation:
When the work of Task 2 can start only after all the work of Task 1 is finished, the tasks have a Finish-to-Start (FS) dependency.
Task 1 is the predecessor of Task 2, and Task 2 is the successor of Task 1.
For example, you can start to print a manual only after it has been written.


Leave a Reply